D9.5 Risk Management report II - ABSTRACT
The first Risk Management report (D9.4) was developed at Month 2 and was mainly focused on the risks that were identified in the project definition phase. This document (D9.5) is the second Risk Management report and includes a revision of all the risks included in the first
report, how they have been overcome so far and other new risks that have been identified by the Work Package leaders together with its proposed contingency measures.
The objective of this document is to provide an overview of the project risks identified and related corrective measures. The following items have been developed:
- Initial risks monitoring (as identified at the beginning of the project and reported in the
DoA); - Identification of new risks arising in the course of the project;
- Identification or application of contingency plans to the initial and/or new risks;
- Identification and/or application of corrective measures to the initial and/or new risks.